How to Increase Transit Capacity and Improve Commutes
We are living on borrowed time.
The links between New York and New Jersey face a growing crisis of capacity, connectivity, and potential collapse. Each of the three primary trans-Hudson facilities—the Northeast Corridor rail tunnel that serves all Amtrak and New Jersey Transit trains into Manhattan; Penn Station; and the Port Authority Bus Terminal— suffer frequent service failures, serve far more people than they were designed to handle, and need major repairs to prevent a catastrophe. The derailments, delays and emergency repairs at Penn Station this summer are mild compared to what will happen if one of the tunnels under the Hudson River fails before replacement tunnels can be built. Losing such a vital part of the regional network would have ripple effects across the entire metropolitan region, affecting everyone who commutes by any mode across the Hudson River, businesses on both sides that rely on these connections, and communities that thrive because of our robust metropolitan economy.
Each day over 1.6 million people commute into Manhattan, the 21st century’s leading global city. For the last 25 years, more and more of those people have been coming from west of the Hudson River. Over that time, the number of jobs in Manhattan has only increased by about 75,000, and the number of daily commuters traveling from New Jersey grew by 70,000, from 250,000 to 320,000.
As a result, rail trips in and out of Penn Station have nearly tripled in the last 25 years, bus trips have grown by 83%, and PATH ridership is up by 27%. RPA’s research projects that this trend will continue over the next two decades, requiring far more capacity than the existing facilities can provide. Work trips to Manhattan could increase by 72,000, or 24%, by 2040, while trips to all of New York City could increase by 148,000, a 38% increase, as job growth in the other New York City boroughs rises even faster.
Our current system of trains, buses, subways, ferries and roads does not have enough capacity to serve another 72,000 — let alone another 150,000 — commuters every day. Without that capacity, overcrowding and delays will get even worse and jobs will depart to other regions. Furthermore, the rail network fails to serve many communities in New Jersey, forcing commuters to rely on buses to a much greater degree than other parts of the metropolitan region. And commuter rail services from all directions terminate in Manhattan, rather than directly connecting the suburbs to each other, which limits the destinations that passengers can get to without transferring and reduces the number of trains that operate in peak periods.
To date, only piecemeal solutions have been proposed to address these problems. Amtrak has proposed the Gateway project: two new tracks under the Hudson River connecting New Jersey to Penn station. Gateway solves the immediate maintenance needs of the tunnels and doubles capacity in the Northeast Corridor, but will not meet longterm demand and limits service options by maintaining Penn Station as a terminus, rather than allowing through running between New Jersey and Long Island. The Port Authority’s proposal for a much larger Midtown bus terminal would accommodate projected bus passengers, but at a very high cost with unacceptable impacts on the neighboring community. And it locks in bus service for many areas of New Jersey, rather than providing more direct, reliable and efficient rail service. And current plans to improve Penn Station and build Moynihan Station would make some improvements in circulation and the passenger experience, but would not be able to handle the additional riders brought in by Gateway.
Each of these projects has been planned and studied in isolation of the others.
Rather than looking holistically at the links across the Hudson River, and where people are coming from and going to, the agencies have been focused on solving their individual problems.
It shouldn’t surprise anyone that they haven’t been able to come up with a comprehensive solution.
These actions can be phased in, and each step builds on the previous investment. This plan would provide enough capacity until mid-century, when trans-Hudson demand will once again begin to surpass combined rail and bus capacity and the existing PABT will have surpassed its useful life. At that point, another phase can add more capacity, either by rebuilding the bus terminal or planning for the fifth and sixth tunnels under the Hudson River.
Both sides of the Hudson River benefit from their proximity to each other — to the extraordinary jobs and vitality of New York City and the workforce and communities in New Jersey. We are cheating the clock by relying on connections that are more than a hundred years old. To prosper in this century, we need to make bold plans once again. Here is the way — now all we need is the will to do it.